In early 2017, Applus+ was awarded the inner tank shell PAUT inspection work by Mitsubishi Heavy Industries.
MHI were aware of the potential benefits Automated Phased Array inspection could have on their project with regards to schedule reduction.
The inner tank shell inspections began in June 2017, and completion was achieved by mid-January 2018.
It is a great achievement that we could help our client MHI deliver two fully constructed inner tank shells in just over 6 months! This reflects a really strong team effort from everyone involved at Applus+. A job well executed team!